Good groundwork gives your hut a firm, level footing. Four properly designed concrete pads can support the wheels without covering the whole area in concrete, while leaving the space underneath open to the air.
Position first. Foundation specification second.
Our drawings show proposed 600 × 600 mm pad footprints and their centre positions. Before work starts, confirm the drawing for your hut and ask your groundworker to check the ground. Pad depth, the material beneath it, concrete specification and any reinforcement must suit the site and the hut’s load.
MARK OUT • DIG • FORM • CURE
Making the pads, step by step
STEP 01
Mark the hut and wheel centres
Use the drawing for your chosen model to mark the hut’s outline with pegs and string. Check which side is the back and identify the left-hand end shown on the plan. Measure the wheel centres from these same reference points. Check the length, width and both diagonals so the layout is square.
STEP 02
Mark a square around each centre
For a confirmed 600 × 600 mm pad, measure 300 mm in each direction from the wheel centre to mark the four edges. The centre of the pad should be directly beneath the centre of the wheel. Put reference pegs outside the excavation so you can find the centres again after digging.
STEP 03
Dig down to suitable ground
Check for buried cables, pipes and drains before breaking ground. Lift the turf, remove topsoil and excavate to the depth agreed for the foundation. Leave room for any required formwork. Keep the bottom free of loose soil and organic material. If you find soft ground, old backfill, roots or standing water, stop and have the foundation reassessed; do not simply fill over it.
STEP 04
Prepare the base and set the levels
Where the foundation design calls for a compacted granular base, use the specified material and build it up in layers, compacting each properly. Avoid loose rubble or garden waste. Set and brace any timber formwork, then check with a laser level that all four finished pad tops will be at the same height. On a slope, the holes may be different depths.
STEP 05
Place and finish the concrete
Use the concrete specified for the job. Position any required reinforcement on proper supports before pouring. Place and compact the concrete as directed, then strike the top off to a flat, level bearing surface. Recheck the pad positions and levels while adjustments are still possible.
STEP 06
Cure it and finish around it
Protect the fresh concrete from drying too quickly, heavy rain and frost, following the supplier’s curing instructions. Ask when it will have enough strength to carry the hut; a hard-looking surface does not prove it is ready. Finish the surrounding ground so water does not collect around the pads. Keep the wheel-bearing surfaces exposed, with no turf or loose gravel between the wheel and concrete.
How deep should the holes be?
There is no single depth that suits every garden or field. The foundation must reach suitable ground and have enough bearing capacity. Clay, nearby trees, slopes or recently filled ground may need a different solution. Have this checked before choosing the excavation depth or ordering concrete.
Keep the underside clear
Arrange the surrounding ground so rainwater can drain away and air can move beneath the floor. Avoid raising soil, planting or stored items against the hut. Steps, paths and landscaping should leave access to the service connections.
Plan the service trenches at the same time
Agree the electricity, drinking-water and foul-drain routes with the relevant trades before digging. Keep excavations from undermining the pads, and leave space to make and maintain the final connections. The utility positions on the drawings are approximate.
Our Electricity, Water & Sewage guide explains the connections. If mains services are unavailable, see our Off-Grid guide.
YOUR MODEL DRAWING
Download the pad and utility plans
Each drawing opens in a new tab. The PDFs are setting-out drafts: confirm the dimensions and foundation specification for your individual hut before pouring. Use the written measurements, not a ruler on the printout.
The Shetland
Hut body: 6,050 × 2,500 mm.
Pad-centre plan, front and back elevations, and approximate utility positions.
The Cheviot
Hut body: 7,250 × 2,750 mm.
Pad-centre plan, front and back elevations, and approximate utility positions.
The Dorset
Hut body: 7,250 × 2,900 mm.
Pad-centre plan, front and back elevations, and approximate utility positions.
The Lincoln
Hut body: 7,550 × 3,050 mm.
Pad-centre plan, front and back elevations, and approximate utility positions.
Four firm supports. One level hut.
Confirm the layout with us and the foundation details with your groundworker before starting.